Priority of using Illustrator flow element
-
- Member
- Posts: 122
- Joined: Fri Jun 12, 2020 11:23 am
Priority of using Illustrator flow element
I have 2 different flows, which both use Illustrator. Is there way for making Switch use the flow element in a certain order? Currently, if both workflows have illustrator files in them to be processed, switch uses Illustrator randomly (or based on when the files were inserted?) The goal would be that switch would first process all workflow A files and then workflow B files. Is this possible?
Re: Priority of using Illustrator flow element
You could use the Hold Job element to distribute files between the two flows. On the connection to folder B you can define a Folder Constraint and only allow files to go to this folder, when folder A i empty. You can then use the app Switch2Switch to send files from A and B to the different flows.